East Bank Road Improvement Project
Good Success to Timehri
IDB Funded Loanf
- GY-L1081 Program to Support Climate Resilient Road Infrastructure Development
- Loan signed on March 6, 2023 for US$117M (G$24.4B)
– US$100M (G$20.8B) is specific
– US$17M (G$3.55B) is local
- The 2024 Budget is G$4.1B
Design Review and Supervision Services
- Contract already signed with Sheladia Associates Inc (USA)
- Contract sum US$7,967,000 on December 1, 2023.
- Duration 48 months
- Already mobilized.
Design-Build Road Works Contract
- First contract of its kind with IDB funding in Guyana
- China Road and Bridge Corporation
- Contract sum US$75,887,907.67.
- 36 months contract
- Contractor
Project Established Campsites
- Main Campsite: Located at Track 'J' Land, Coverden Public Road, East Bank Demerara, Guyana. This site will serve as the primary location for bulk storage, concrete batching, housing, office facilities, and other operational needs.
- Sub-main Campsite: Situated on the eastern side of the Soesdyke-Linden Highway, between Madewini Creek and Kuru Kururu, Guyana. This campsite will be dedicated to cement concrete batching, asphalt mixing and the bulk storage of materials.
Road Works will entail:
- Approximately 23.7km of roadway with over 58 structures
- Road will be an upgraded 2-lane roadway
- Increased safety features for vulnerable road users, namely pedestrians and cyclists including sidewalks and cycle lanes;
- Construction of concrete drains
- Installation of thermoplastic road marking; LED street lighting; and traffic signs
- Reconstruction of bridges and culverts as well as widening of culverts along the road from Good Success to Timehri.
Public Communication and Dissemination of Information
- In addition to the use of print and social media, the Ministry will utilize the RESOLV 75 WhatsApp application to communicate with the public, which facilitated with assistance from the IDB.
Stakeholder Consultations
- Road Rehab Project will improve road safety and reducing traffic congestion.
- Benefits will include better access to jobs, markets, and services for communities.
- It is acknowledged that there will be concerns and questions from residents and businesses regarding potential impacts during construction, such as access disruptions and noise but there are measures to mitigate the disruption as best as possible.
- There is a Grievance Redress Mechanism: Stakeholders will be made aware of the process and will have easy accessibility through several channels. All grievances will be confidential and handled impartially.
- We commit to regular communication and engagement with stakeholders throughout the project to address issues promptly.


Timehri Junction Road Improvement
A vision for the Future
An artist's concept showcasing the transformed Timehri Junction—modern, efficient, and community-focused.
Enhanced Road Design
Widening with Bus Bays and Sidewalks
A conceptual illustration of improved infrastructure, featuring expanded roadways, dedicated bus bays, and safe pedestrian sidewalks.

3D Visualization
Improved Roadway Layout
A dynamic 3D video showcasing the innovative design and layout of the upgraded roadway, blending functionality and modern aesthetics.
Your feedback and concerns are important to us.
To ensure effective communication throughout this project, we have established a Grievance Redress Mechanism. Please reach out with any questions or feedback.
How to lodge a complaint:
- Identify the issue: What is the problem and how is it affecting you?
- Gather information: Take notes of times, dates, and specific locations.
- Submit your complaint:
- Contractor Hotline: +592 656 7429
- Consultant Hotline: +592 728 2031
- Email: eastbankproject.grm@gmail.com
- Complaint boxes located at NDCs and the Campsites
NOTE: All complaints are confidential, and personal details will not be shared without permission.
Other points of contact:
- Mr. Roger Hodgson, Resident Engineer – Sheladia Associates Inc.: +592 705 3455
- Ms. Yashodra Singh, Socio-Environmental Officer – Ministry of Public Works: +592 620 2135
Contact Us



IDB Funded Loanf
- GY-L1081 Program to Support Climate Resilient Road Infrastructure Development
- Loan signed on March 6, 2023 for US$117M (G$24.4B)
– US$100M (G$20.8B) is specific
– US$17M (G$3.55B) is local
- The 2024 Budget is G$4.1B
Design Review and Supervision Services
- Contract already signed with Sheladia Associates Inc (USA)
- Contract sum US$7,967,000 on December 1, 2023.
- Duration 48 months
- Already mobilized.
Design-Build Road Works Contract
- First contract of its kind with IDB funding in Guyana
- China Road and Bridge Corporation
- Contract sum US$75,887,907.67.
- 36 months contract
- Contractor
Project Established Campsites
- Main Campsite: Located at Track 'J' Land, Coverden Public Road, East Bank Demerara, Guyana. This site will serve as the primary location for bulk storage, concrete batching, housing, office facilities, and other operational needs.
- Sub-main Campsite: Situated on the eastern side of the Soesdyke-Linden Highway, between Madewini Creek and Kuru Kururu, Guyana. This campsite will be dedicated to cement concrete batching, asphalt mixing and the bulk storage of materials.
Road Works will entail:
- Approximately 23.7km of roadway with over 58 structures
- Road will be an upgraded 2-lane roadway
- Increased safety features for vulnerable road users, namely pedestrians and cyclists including sidewalks and cycle lanes;
- Construction of concrete drains
- Installation of thermoplastic road marking; LED street lighting; and traffic signs
- Reconstruction of bridges and culverts as well as widening of culverts along the road from Good Success to Timehri.
Public Communication and Dissemination of Information
- In addition to the use of print and social media, the Ministry will utilize the RESOLV 75 WhatsApp application to communicate with the public, which facilitated with assistance from the IDB.
Stakeholder Consultations
- Road Rehab Project will improve road safety and reducing traffic congestion.
- Benefits will include better access to jobs, markets, and services for communities.
- It is acknowledged that there will be concerns and questions from residents and businesses regarding potential impacts during construction, such as access disruptions and noise but there are measures to mitigate the disruption as best as possible.
- There is a Grievance Redress Mechanism: Stakeholders will be made aware of the process and will have easy accessibility through several channels. All grievances will be confidential and handled impartially.
- We commit to regular communication and engagement with stakeholders throughout the project to address issues promptly.


Timehri Junction Road Improvement
A vision for the Future
An artist's concept showcasing the transformed Timehri Junction—modern, efficient, and community-focused.
Enhanced Road Design
Widening with Bus Bays and Sidewalks
A conceptual illustration of improved infrastructure, featuring expanded roadways, dedicated bus bays, and safe pedestrian sidewalks.

3D Visualization
Improved Roadway Layout
A dynamic 3D video showcasing the innovative design and layout of the upgraded roadway, blending functionality and modern aesthetics.
Your feedback and concerns are important to us.
To ensure effective communication throughout this project, we have established a Grievance Redress Mechanism. Please reach out with any questions or feedback.
How to lodge a complaint:
- Identify the issue: What is the problem and how is it affecting you?
- Gather information: Take notes of times, dates, and specific locations.
- Submit your complaint:
- Contractor Hotline: +592 656 7429
- Consultant Hotline: +592 728 2031
- Email: eastbankproject.grm@gmail.com
- Complaint boxes located at NDCs and the Campsites
NOTE: All complaints are confidential, and personal details will not be shared without permission.
Other points of contact:
- Mr. Roger Hodgson, Resident Engineer – Sheladia Associates Inc.: +592 705 3455
- Ms. Yashodra Singh, Socio-Environmental Officer – Ministry of Public Works: +592 620 2135
Contact Us



. IDB Funded Loan
- GY-L1081 Program to Support Climate Resilient Road Infrastructure Development
- Loan signed on March 6, 2023 for US$117M (G$24.4B)
– US$100M (G$20.8B) is specific
– US$17M (G$3.55B) is local
- The 2024 Budget is G$4.1B
Design Review and Supervision Services
- Contract already signed with Sheladia Associates Inc (USA)
- Contract sum US$7,967,000 on December 1, 2023.
- Duration 48 months
- Already mobilized.
Design-Build Road Works Contract
- First contract of its kind with IDB funding in Guyana
- China Road and Bridge Corporation
- Contract sum US$75,887,907.67.
- 36 months contract
- Contractor
Road Works will entail:
- Approximately 23.7km of roadway with over 58 structures
- Road will be an upgraded 2-lane roadway
- increased safety features for vulnerable road users, namely pedestrians and cyclists including sidewalks and cycle lanes;
- Construction of concrete drains
- Installation of thermoplastic road marking; LED street lighting; and traffic signs
- Reconstruction of bridges and culverts as well as widening of culverts along the road from Good Success to Timehri.
Public Communication and Dissemination of Information
- In addition to the use of print and social media, the Ministry will utilize the RESOLV 75 WhatsApp application to communicate with the public, which facilitated with assistance from the IDB
Stakeholder Consultations
- Road Rehab Project will improve road safety and reducing traffic congestion.
- Benefits will include better access to jobs, markets, and services for communities.
- It is acknowledged that there will be concerns and questions from residents and businesses regarding potential impacts during construction, such as access disruptions and noise but there are measures to mitigate the disruption as best as possible.
- There is a Grievance Redress Mechanism: Stakeholders will be made aware of the process and will have easy accessibility through several channels. All grievances will be confidential and handled impartially.
- We commit to regular communication and engagement with stakeholders throughout the project to address issues promptly

Your feedback and concerns are important to us.
To ensure effective communication throughout this project, we have established a Grievance Redress Mechanism. Please reach out with any questions or feedback.
How to lodge a complaint:
- Identify the issue: What is the problem and how it is affecting you?
- Gather information: Take notes of times, dates, and specific locations.
- Submit your complaint:
- Contractor Hotline: +592 656 7429
- Consultant Hotline: +592 728 2031
- Email: eastbankgrm@gmail.com
- Complaint boxes located at NDCs and the Campsites
NOTE: All complaints are confidential, and personal details will not be shared without permission.
Other points of contact:
- Mr. Roger Hodgson, Resident Engineer – Sheladia Associates Inc.: +592 705 3455
- Ms. Yashodra Singh, Socio-Environmental Officer – Ministry of Public Works: +592 620 2135
Contact Us



Concept Widening with Bus Bays and Sidewalks
As part of our commitment to improving public infrastructure, the concept of road widening integrates dedicated bus bays and sidewalks to enhance commuter convenience and safety.


Concept Junction Improvement - Timehri
The junction improvement at Timehri focuses on optimizing traffic flow and enhancing safety for all road users. This project aims to modernize the intersection, reduce congestion, and provide a more efficient and secure travel experience for both motorists and pedestrians.
Concept Video : East Bank Road Improvement Project – Good Success to Timehri
This concept video highlights key enhancements from Good Success to Timehri, aiming to improve connectivity, traffic flow, and community accessibility.

Accomodations

Car Rental
Concept Junction Improvement- Timehri
The junction improvement at Timehri focuses on optimizing traffic flow and enhancing safety for all road users. This project aims to modernize the intersection, reduce congestion, and provide a more efficient and secure travel experience for both motorists and pedestrians.


Concept Widening with Bus Bays and Sidewalk
As part of our commitment to improving public infrastructure, the concept of road widening integrates dedicated bus bays and sidewalks to enhance commuter convenience and safety. This initiative is designed to streamline traffic flow while promoting pedestrian-friendly spaces.
Animation of the East Bank Road Improvement Project – Good Success to Timehri
his concept video highlights key enhancements from Good Success to Timehri, aiming to improve connectivity, traffic flow, and community accessibility.

Concept of the completed project

Concept Widening with Bus Bays and Sidewalk

Concept Junction Improvement Timehri
Your feedback and concerns are important to us.
To ensure effective communication throughout this project, we have established a Grievance Redress Mechanism. Please reach out with any questions or feedback.
How to lodge a complaint:
- Identify the issue: What is the problem and how it is affecting you?
- Gather information: Take notes of times, dates, and specific locations.
- Submit your complaint:
- Contractor Hotline: +592 656 7429
- Consultant Hotline: +592 728 2031
- Email: eastbankgrm@gmail.com
- Complaint boxes located at NDCs and the Campsites
NOTE: All complaints are confidential, and personal details will not be shared without permission.
Other points of contact:
- Mr. Roger Hodgson, Resident Engineer – Sheladia Associates Inc.: +592 705 3455
- Ms. Yashodra Singh, Socio-Environmental Officer – Ministry of Public Works: +592 620 2135



Your feedback and concerns are important to us.
To ensure effective communication throughout this project, we have established a Grievance Redress Mechanism. Please reach out with any questions or feedback.
How to lodge a complaint:
- Identify the issue: What is the problem and how it is affecting you?
- Gather information: Take notes of times, dates, and specific locations.
- Submit your complaint:
- Contractor Hotline: +592 656 7429
- Consultant Hotline: +592 728 2031
- Email: eastbankgrm@gmail.com
- Complaint boxes located at NDCs and the Campsites
NOTE: All complaints are confidential, and personal details will not be shared without permission.
Other points of contact:
- Mr. Roger Hodgson, Resident Engineer – Sheladia Associates Inc.: +592 705 3455
- Ms. Yashodra Singh, Socio-Environmental Officer – Ministry of Public Works: +592 620 2135