New fuel bond for Harbour Bridge

18th November, 2013

PETER’S HALL - The construction of two fuel bonds - 500 and 2,000 gallons - with base support in the East Generator Compound has commenced, announced Rawlston Adams, General Manager of the Demerara Harbour Bridge (DHB).

According to him, JPM’s Construction Inc would construct foundation, walls and support for the tanks and the sump at the rear of the bund.

The foundation, walls and support for the tanks are complete. Currently, the piping works are on-going, while the sump will be constructed upon completion of pipe works.

The perimeter fence is also completed.