Remedial works for EBB road for Sept. 14 completion

9th September, 2015

KINGSTON - Corrective works to the East Bank Berbice (EBB) road will be completed by September 14, 2015.

A joint site visit was done on the East Bank Berbice Roadway on September 7, 2015 between representatives from the Ministry of Public Infrastructure and representatives from H. Nauth & Sons to determine the exact scope of the corrective works to be done.

This project comprise mainly of 12 kilometers of asphalt overlay with sectional rehabilitation.

Among the major corrective works being addressed were some areas where the thickness of the asphalt surface was below the required thickness and the compaction was less than that required in some sections.